Thursday 24 December 2015

Modify/Manage Meter Reading History - IBM Maximo



  1. From the Select Action menu, select Manage Meter Reading History.
  2. Select the meter that you want to modify, and display the row details.
  3. In the Modified Delta field, specify a reading. 
  4. Optional: To enter an actual reading for the selected meter, enter a value in the Modified Reading field.
  5. Click OK. 

Reference:
http://www-01.ibm.com/support/knowledgecenter/SSLL9Z_7.6.1/com.ibm.trn.doc/gp_consists/t_manage_meter_hist.html

1 comment:

  1. I have a question related to asset meter reading history. We have imported assets,meter,meter reading,meter reading history using MIF. We are facing following issue. Suppose Asset A123 is associated with 3 meters namely M1,M2,M3 in site 3214. Each meter has 10 readings in meter reading history. We get this data , change it for site 7214 and upload it using MIF. We change the status of asset A123 to DECOMISSIONED at site 3214. The status of asset A123 at site 7214 is OPERATING. Issue we are facing is : At the site 7214, asset meter reading history is not updated with all the readings. There are only 3 rows for meter reading history i.e. only 1 row for each meter is available. Please let us know how to resolve this issue.

    ReplyDelete